PANTHER CREEK | PROJECT OVERVIEW

Panther Creek Solar is a proposed 144 MW solar project located in Hardin County, Ohio. The project sits on approximately 1800 acres located on either side of State Road 68, about eight and a half miles south of Kenton. Panther Creek is estimated to submit an application to the Ohio Power Siting Board in mid-2025.

Panther Creek Solar is a utility-scale solar photovoltaic project that would provide reliable, cost-effective electricity to the region, along with long-term economic benefits to Hardin County throughout the life of the project

144 MW

clean electricity delivered to Ohio grid

$380 MM

estimated investment in Hardin and Logan counties

275

estimated local jobs during construction

PROJECT TIMELINE

March 2022

Community Information Meeting

2025

Submit OPSB Application

2027

Expected Construction Start

2029

Expected Operational Date

PROJECT TIMELINE

March 2022: Community Information Meeting

2025: Submit OPSB Application

2027: Expected Construction Start

2029: Expected Operational Date

RESOURCES

MORE INFORMATION

Phone: 419-679-3038

Email: [email protected]

FAQs: View Common Solar Questions

PINE GATE RENEWABLES

Founded in 2016, Pine Gate Renewables is a developer and owner-operator of utility scale solar and energy storage projects across the United States.  We are dedicated to the deployment of clean energy and have extensive experience in the development, financing, construction, and operation of solar and energy storage facilities.

As a trusted partner and leader in the industry, we have closed more than $7 billion in project financing and capital investment.  Our operational fleet includes over 100 solar facilities accounting for more than two gigawatts (GW) of installed capacity.  With more than 30 GW of projects in development, we are generating the Power of TomorrowTM.